Clos de Paradis Phase 2

Architect

Morris Architects

Value

£4M

Programme

72 weeks (62 actual)

AC Mauger Construction Projects | Clos de Paradis Phase 2 AC Mauger Construction Projects | Clos de Paradis Phase 2 AC Mauger Construction Projects | Clos de Paradis Phase 2 AC Mauger Construction Projects | Clos de Paradis Phase 2 AC Mauger Construction Projects | Clos de Paradis Phase 2 AC Mauger Construction Projects | Clos de Paradis Phase 2 AC Mauger Construction Projects | Clos de Paradis Phase 2 AC Mauger Construction Projects | Clos de Paradis Phase 2
AC Mauger Construction Projects | Clos de Paradis Phase 2

Clos de Paradis Phase 2

 

Work completed approximately 10 weeks ahead of schedule on the second phase of the refurbishment project at Clos de Paradis.

Phase 2 of the Clos de Paradis project consisted of the total refurbishment of sixteen houses with, once again, the scope of work including new roofing, windows, internal walls and staircases, new kitchens, bathrooms and built-in storage, new floor finishes and doors and insulated render to each of the properties.

The project also included 12 new build homes.

External to the properties there were substantial retaining wall works, remodelling of roads and footpaths, brick paving works and further infrastructure works including telecoms, JEC, waterworks and drainage.